Clay County Florida issued the following announcement.
Ongoing County Projects
CR 315-C from CR 214 to Putnam County Line- 2.74-mile project includes lane widening, adding paved shoulders, modifying driveway culverts, and resurfacing with a high friction overlay to reduce skid hazards. Roadwork began on July 13, 2020 and is expected to be substantially complete in April of 2021.
Haven Road in Green Cove Springs- A full detour is in place between Orion Road and Pringle Circle for a drainpipe replacement project that began in late-July. The project will take approximately 10 weeks to complete.
FDOT Projects
Blanding Blvd Widening Project- Between Allie Murray Road and Long Bay Road- A new alignment of Long Bay Road and Blanding Boulevard is open to traffic. A segment of County Road 220 west at Blanding Boulevard closed to traffic on July 14, 2020 and will remain closed for several months as the contractor constructs a new alignment at this intersection. Motorists will be detoured via Long Bay Road and Blanding Boulevard.
Blanding Blvd Widening Project – CR 218 to Black Creek Bridge- Add lanes and reconstruct 1.2 miles of roadway from County Road 218 to Black Creek Bridge Project began construction in late February 2020 and is expected to be completed in fall 2021.
Governors Creek Bridge- FDOT project to install sidewalks and make other improvements to U.S. 17 on the Governors Creek Bridge at a cost of approximately $954,000. Construction began on July 6, 2020 and is expected to be completed in spring 2021. Anticipate nighttime lane closures weeknights between 7 p.m. and 7 a.m. for road work.
SR 21 Between Keystone Heights and Melrose- Milling and resurfacing project began in May of 2020 on the 6.5 mile stretch between the Putnam County line, just north of Melrose, to north of Commercial Circle in Keystone Heights. Portions of this project are in Bradford, Clay and Putnam counties. In addition to milling and resurfacing, the project improves the safety of the roadway by widening paved shoulders, improving lighting within Keystone Heights and adding mid-block crossings and bulb-outs. Construction began in June 2020 at a cost of $6.9 million with completion expected in summer 2021.
First Coast Expressway Work FDOT
County Road 209 east of U.S. 17 - Daytime lane closures with flaggers weekdays from 8:30 a.m. to 4:30 p.m. for road work.
First Coast Expressway (State Road 23) from north of S.R. 16 to north of S.R. 21 - Construct 11.1 miles of new limited access toll road from north of S.R. 16 to north of S.R. 21 (Blanding Boulevard) at a cost of $247.1 million. Construction began March 4, 2019.
First Coast Expressway (State Road 23) from east of C.R. 209 to north of S.R. 16 - Construct 9.7 miles of new limited access toll road from east of C.R. 209 to north of S.R. 16 at a cost of $195.2 million. Construction began April 15, 2019.
Sandridge Road from State Road 23 to Rolling View Boulevard – Intermittent traffic interruptions Monday through Saturday from 7 a.m. to 5:30 p.m. to allow construction vehicles to cross Sandridge Rd. Flaggers will be in place both east and west bound.
Spring Bank Road just south of State Road 16 - Daytime lane closures with flaggers weekdays from 7:30 a.m. to 4:30 p.m. and nighttime lane closures weeknights from 6 p.m. to 6:30 a.m. for road work.
State Road 16 west of Green Cove Springs - Daytime lane closures with flaggers weekdays from 8 a.m. to 4:30 p.m. for road work.
U.S. 17 south of Green Cove Springs - Daytime lane closures weekdays from 7:30 a.m. to 4:30 p.m. and nighttime lane closures weeknights from 6 p.m. to 6:30 a.m. for road work.
Original source can be found here.